Main steps of the DIVE project so far

May, 2017 DIVE-ICDP workshop in Baveno, Italy read more..
October, 2017 Pre-SEIZE - 1-km deep active seismic survey in Val Sesia
January, 2018 DIVE Full drilling proposal submitted to ICDP (1st attempt)
January, 2020 DIVE - Phase 1 Full drilling proposal submitted to ICDP (2nd attempt)
September, 2020 DIVE - Phase 1 Full drilling proposal approved and partially funded by ICDP
October, 2020 SEIZE and Hi-SEIZE – deep active seismic surveys in Val Sesia
January, 2021 Gravimetric survey of the Balmuccia peridotite
June, 2021 FWF (Austria) co-funds the project Phase 1
September, 2021 SNSF (Switzerland) co-funds the project Phase 1
October, 2021 Installation of a seismic monitoring network (INGV + UNIL)
December, 2021 Opening of the tender for finding the Phase-1 contractor read more..
February, 2022 ICDP Workshop on Drilling Information System read more..